A fairly new policy change from Dominion Power could mean delays in the process of receiving final site plan approval, which could delay the construction process. Virginia Dominion Power has notified local jurisdictions of a change in policy regarding where underground vaults must be placed for new developments. Vaults must now be placed on property owned by the development and include an easement granting access to the vault.
As a result, site plans with vaults on public property, such as under a sidewalk or street, may be flagged during the approval process. The reasoning behind the change is that Dominion Power wants to be granted an easement on the property from the developer to secure access to the vault, which they cannot do on public property because the developer does not own it.
This article was originally published on our Virginia Real Estate, Land Use & Construction Law blog.